Amadeo II construction update : result
05 December 2010
Amadeo II construction update: underfloor heating, screed and painting
16 September 2010
Amadeo II construction update: installation, facade and glazings
29 July 2010
Amadeo II construction update: roof cover and windows
06 June 2010
Amadeo II construction update: roof and interior walls
28 April 2010
Installing Schiedel ventilation and chimney elements in Amadeo II
13 April 2010
Raising walls of Amadeo II with Klimabloc
23 March 2010
Amadeo II 1st floor slab and installation of AVI Thermokorb
28 February 2010
External walls of Amadeo II ground floor with Klimabloc
19 January 2010
Underground parking of Amadeo II is finished
06 December 2009
Making of the armed concrete ground floor slab of Amadeo II
22 November 2009
Making of the armed concrete base slab of Amadeo II - part 2
01 November 2009
Making of Amadeo II underground parking walls
22 October 2009
Making of the armed concrete base slab of Amadeo II
04 October 2009
Installation of the waterproofing layer on Amadeo II footer slab
28 September 2009
Making of the drainage layer and footer slab of Amadeo II
22 September 2009
Construction of Amadeo II has started
16 September 2009
Amadeo construction update: finitions part 2
11 September 2009
Amadeo construction update: finitions part 1
14 June 2009
Amadeo construction update: tiling, electricity and facade
30 April 2009
Installation of the solar system and starting tiling
17 April 2009
Making the final sand and cement floor screed
03 April 2009
Installation of Rehau underfloor heating with RAUTHERM pipes and Vario boards
20 March 2009
Finishing the interior walls with cement plaster
24 February 2009
Installation of electricity, plumbing and underfloor heating
20 January 2009
Installation of Rehau plumbing and underfloor heating verticals
03 December 2008
Installation of Rehau SOLECT thermal solar panels on Amadeo's roof
20 November 2008
Amadeo construction update: exterior, facade, plumbing and heating
17 November 2008
Amadeo construction update: windows, roof and ramp
05 November 2008
Starting partition walls in Amadeo
28 September 2008
Making the drainage layer for Amadeo II
27 September 2008
Making of Amadeo's first floor slab - second part
10 September 2008
Preparation of the land for Amadeo II
07 September 2008
Installation of Schöck Isokorb elements on the balconies of Amadeo
03 September 2008
Making of Amadeo's first floor slab with precast beams and ceiling bricks
01 September 2008
Raising walls of Amadeo's ground floor with POROTHERM
25 August 2008
Making of Amadeo second ground floor armed concrete slab
15 August 2008
Building the first POROTHERM walls for Amadeo
10 August 2008
Making of Amadeo ground floor armed concrete slab
04 August 2008
Amadeo construction update: completion of underground parkings
28 July 2008
Installation of the first Raugeo geothermal probe for Amadeo
12 July 2008
Installation of Index Testudo waterproofing layer on the parking walls
06 July 2008
Making of Amadeo's underground parking walls - part 2
03 July 2008
Making of Amadeo's underground parking walls
26 June 2008
Drilling Amadeo's boreholes for the installation of the geothermal probes
23 June 2008
Making of Amadeo's first armed concrete slab
20 June 2008
Installation of the iron reinforcement on the right part of Amadeo (2nd layer)
19 June 2008
Installation of the iron reinforcement on the right part of Amadeo (1st layer)
09 June 2008
Installation of Index Testudo Spunbond waterproofing layer
02 June 2008
Making of Amadeo's drainage layer and footer
01 June 2008
Digging Amadeo's foundations and finition of the new roads
12 May 2008
Preparation of Amadeo's land continuation and new roads
20 April 2008
Preparation of Amadeo's land is started
14 April 2008
Beodom obtained the usage permit for Amadeo
15 January 2010
Kuće Beodom obtained Amadeo II's building permit
13 October 2008
Kuće Beodom obtained the certificate of conformity for Amadeo II
01 October 2008
Kuće Beodom obtained Amadeo's building permit
27 March 2008
Amadeo scale model arrived in Kuće Beodom's office
21 March 2008
Kuće Beodom obtained the certificate of conformity for Amadeo
11 March 2008
Amadeo scale model construction - part 2
08 March 2008
Amadeo scale model construction - part 1
02 March 2008
Complete Amadeo project is now online
12 December 2007
First external view and 3D view of Amadeo
05 December 2007
Second draft preview of the architectural design of Amadeo
30 November 2007
Draft preview of the architectural design of Amadeo
16 November 2007
Beodom director will speak during the SEEBBE 2010 conference
03 April 2010
Amadeo is featured in the European Carbon Atlas from COST
17 March 2010
Amadeo visible on Google Earth through Panoramio
26 February 2010
Sale of Amadeo II started at exceptional price
06 May 2009
Amadeo won special prize in the Investment of the Year Award
09 March 2009
Amadeo nominated for the Investment of the Year 2008
26 February 2009
Kuće Beodom's Technical Director talks at BelRE 2008 conference
01 November 2008
Minister Oliver Dulić visits Kuće Beodom at BelRE 2008
30 October 2008
Kuće Beodom will be present and speak at BelRE 2008
09 October 2008
Rehau SOLECT thermal solar system for Amadeo!
27 August 2008
Wienerberger team visits Amadeo construction site
12 August 2008
Kuće Beodom received the first shipment of Wienerberger POROTHERM
05 July 2008
Low-temperature floor heating system powered by a geothermal heat pump for Amadeo!
22 May 2008
Amadeo will be the first low-energy residential building in Belgrade
25 February 2008
Italian Design touch for Kuće Beodom's Amadeo project
07 November 2007
A brand new road around Amadeo's land
15 October 2007